Pillar Box Installation

NHS Regent Point, Newcastle upon Tyne

Featured Case Study

Logo
Pillar Box Installation

NHS Regent Point, Newcastle upon Tyne • NHS Regent Point, Newcastle upon Tyne • Service: Electrical Infrastructure – Pillar Box & SWA Installation

Envo Facilities was appointed to install a new electrical pillar box system at NHS Regent Point to support ongoing infrastructure upgrades across the site. The project required the installation of SWA cabling, new isolators, and responsible waste removal, all completed safely and efficiently within an operational NHS environment.

The Challenge

  • Install a new electrical pillar box for external supply access.
  • Lay and terminate 10mm 5-core SWA cable.
  • Install multiple isolators for safe distribution.
  • Ensure all work complied with electrical safety standards.
  • Manage and remove all waste in accordance with site protocols.
  • Complete works with minimal disruption to NHS activities.

Our Approach

Installation & Supply

The project included the supply and installation of 50m of 10mm 5-core SWA armoured cable, 1 × external-rated electrical pillar box, 3 × isolators for controlled shutdown and protection, and full waste removal and site tidy. All cabling and terminations were installed in line with BS 7671 regulations, ensuring reliability, durability, and future expandability.

Results Delivered

  • Fully installed and operational pillar box system.
  • Safe, compliant, and future-ready electrical supply point.
  • Secure installation suitable for external conditions.
  • Seamless integration with existing site infrastructure.
  • Delivered safely with zero operational disruption to NHS staff or visitors.
Pillar Box Installation Results

Our Environmental Commitment

As part of the Envo approach, all materials were handled responsibly and waste was recycled where possible. We minimised disruption to the facility and worked in accordance with all environmental and sustainability guidelines.